TROY, NY (May 12) – Operation Refresh, the City of Troy's intense spring cleaning program, continues tomorrow, 5/13. Street milling and paving will continue this week, but please remember that those schedules are subject to change. We ask all residents to check the spring cleaning schedule for their street's designated day, and to follow posted parking restrictions. Signs go out the day before. Violators will be towed. For more information, visit https://troyny.gov/1529/Spring-Cleaning.
Spring Cleaning
| Monday, May 13 Odd side | All streets off 8th St to Orchard Ave From Sage Ave to Congress St including Walnut St, Birch St, Hale St, Marshall St, & Cyprus St |
| Tuesday, May 14 Even side | All streets from Humiston Ave to Hoosick St |
| Wednesday, May 15 Odd side | All streets from Humiston Ave to Hoosick St |
| Thursday, May 16 Even side | All streets from Frear Park Road to Hoosick St |
| Friday, May 17 Odd side | All streets from Frear Park Road to Hoosick St |
Milling/Paving
*please note that this schedule is subject to change.
| Monday, May 13 | Milling: Madison Ave between O’Neil St - Odell St Lark St between Madison Ave - Lexington Ave Paving: |
| Tuesday, May 14 | Project St between Madison Ave - Delaware Ave |
| Wednesday, May 15 | Delaware Ave between Madison Ave - Project St |
| Thursday, May 16 | Madison Ave between Delaware Ave - Odell St |